==S3 Patients on N5/S5 Laptop==
==S3 Patients on N5/S5 Laptop==
*We are now going to have S3 patients on N5/S5 laptops and want to be able
*We are now going to have S3 patients on N5/S5 laptops and want to be able
to send them, as S4 will no longer be in charge of collecting on this ward.Do we need something done to the program to allow us to send S3
to send them, as S4 will no longer be in charge of collecting on this ward.Do we need something done to the program to allow us to send S3 patients from N5/S5 laptop?[[User:WGobert|gogogirl]] 12:51, 21 October 2009 (CDT)
patients from N5/S5 laptop?[[User:WGobert|gogogirl]] 12:51, 21 October 2009 (CDT)
*as per email sent today, there would be no problem in collecting and sending S3 patients on the S5 or N5 netbook (laptop).  The only question I have is for Tina about the pending.mdb.  Where would the S3 pending go on the Regional server?  Let us know before Monday October 26. This is when VIC plans to start doing this.--[[User:TOstryzniuk|TOstryzniuk]] 19:03, 21 October 2009 (CDT)
** Data would go to the same file names as it does now, ie the Vic_N5 folder. By the way, please make sure that you don't change the settings.mdb, just the patient locations in their records. This should be mirrored in the way things work at HSC and StB where collectors are sharing laptops. Having said that, we don't make these changes often, so if we want to be 100% sure this will work Monday then the collector should send a test batch tomorrow. [[User:Ttenbergen|Ttenbergen]] 20:58, 21 October 2009 (CDT)
** Data would go to the same file names as it does now, ie the Vic_N5 folder. By the way, please make sure that you don't change the settings.mdb, just the patient locations in their records. This should be mirrored in the way things work at HSC and StB where collectors are sharing laptops. Having said that, we don't make these changes often, so if we want to be 100% sure this will work Monday then the collector should send a test batch tomorrow. [[User:Ttenbergen|Ttenbergen]] 20:58, 21 October 2009 (CDT)
***We will discuss the serial numbering solution before moving the VIC_S3 collection onto the VIC_N5 and VIC_S5 PDA.  Plan for conference call with Shirley, Wendy, Tara and Trish Tuesday, Oct 27.09.--[[User:TOstryzniuk|TOstryzniuk]] 18:26, 22 October 2009 (CDT)


== QA Functionality ==
== QA Functionality ==