|explanation= Stopped everywhere as of October 1, 2019
|content=
== Overstay V2, no DPST or green ==
=== Start Date ===
*STB, HSC, GRA, VIC:  July 31.17
=== Stop Date ===
*'''ALL sites -stop''' for any new admission as of October 1, 2019. Any outstanding admissions that are prior to October 1, 19 must have overstay color generated. -- [[User:TOstryzniuk|Trish Ostryzniuk]] 16:37, 2019 November 18 (CST)
*VIC - up to October 2, 2017 midnight, then stop
== Original Overstay project ==
green, yellow and red, included DPST form.
===Stop Date===
===Stop Date===
#'''HSC'''  
#'''HSC'''  
#*H4, H4H, A4, D4, D5: '''November 5, 2015'''
#*B3, H4, H4H, A4, D4, D5: '''November 5, 2015'''
 
#**stopped DPST form, putting dots on charts & filling in transition coordinator binder.  
* Just wondering why the overstay project has stopped at HSC when it continues everywhere else?  I thought this was a regional program.  If there is resistance to completing the DPST's or if the Doc's are not doing their part they need to work with them.  We have had much of the same issues at STB and have worked hard to keep it operational because we thought it was an important program. I am very surprised that the program was cancelled there.  What is the rationale for keeping it running at all the other hospitals then?  --[[User:LKolesar|LKolesar]] 08:32, 2015 November 6 (CST)
#**CONTINUED to: generated a color
** https://en.wikipedia.org/wiki/Realpolitik ;-) One place opted out, and we can't force them to keep going. Not a reason to stop elsewhere is it? Ttenbergen 10:36, 2015 November 9 (CST)


===Start Date ===
===Start Date ===
#'''HSC'''  
#'''HSC'''  
#*H4, H4H, A4, D4, D5: '''May 13, 2013'''
#*B3, H4, H4H, A4, D4, D5: '''May 13, 2013'''
#'''VIC'''  
#'''VIC'''  
#*S3, S4, N5, S5 AND the overflow beds '''February 11, 2013'''
#*S3, S4, N5, S5 AND the overflow beds '''February 11, 2013'''
Line 18: Line 31:
#*E6: '''November 13, 2012''' (Training starting the week of October 2012 29th
#*E6: '''November 13, 2012''' (Training starting the week of October 2012 29th
#*E5: '''November 5, 2012''' (Training starting in October 23th and 24th 2012). Database study number 91429.
#*E5: '''November 5, 2012''' (Training starting in October 23th and 24th 2012). Database study number 91429.
#**ward stopped filling in DPST forms between Oct 9- ?.16 for local site "experiment" using an Emergency safety checklist form. Has not resumed.  To be address with Regional Medicine Directors and to next steps.[[User:TOstryzniuk|Trish Ostryzniuk]] 13:41, 2016 October 26 (CDT)
#***CONTINUE to generate a color.


=== End Date ===
}}
There is no end date for the project at present; the committee will review results after 3 months and make adjustments at that time




[[Category: OverstayProject]]
[[Category:OverstayProject]]

Latest revision as of 10:57, 30 July 2025

Legacy Content

This page contains Legacy Content.

  • Explanation: Stopped everywhere as of October 1, 2019
  • Successor: No successor was entered

Click Expand to show legacy content.

Overstay V2, no DPST or green

Start Date

  • STB, HSC, GRA, VIC: July 31.17

Stop Date

  • ALL sites -stop for any new admission as of October 1, 2019. Any outstanding admissions that are prior to October 1, 19 must have overstay color generated. -- Trish Ostryzniuk 16:37, 2019 November 18 (CST)
  • VIC - up to October 2, 2017 midnight, then stop

Original Overstay project

green, yellow and red, included DPST form.

Stop Date

  1. HSC
    • B3, H4, H4H, A4, D4, D5: November 5, 2015
      • stopped DPST form, putting dots on charts & filling in transition coordinator binder.
      • CONTINUED to: generated a color

Start Date

  1. HSC
    • B3, H4, H4H, A4, D4, D5: May 13, 2013
  2. VIC
    • S3, S4, N5, S5 AND the overflow beds February 11, 2013
  3. GRA
    • N3, W3: October 1, 2012
    • N5: July 23, 2012
  4. STB
    • 5B: November 19, 2012 (Training starting in November 5th 2012)
    • E6: November 13, 2012 (Training starting the week of October 2012 29th
    • E5: November 5, 2012 (Training starting in October 23th and 24th 2012). Database study number 91429.
      • ward stopped filling in DPST forms between Oct 9- ?.16 for local site "experiment" using an Emergency safety checklist form. Has not resumed. To be address with Regional Medicine Directors and to next steps.Trish Ostryzniuk 13:41, 2016 October 26 (CDT)
        • CONTINUE to generate a color.